Free Construction Progress Report Template
A construction progress report tracks how much of the work has actually been completed against the planned schedule — usually expressed as a weighted percentage complete, broken down by section. It compares planned % to actual % per item, rolls up to an overall progress figure, and in its fullest form converts that into earned value against the contract sum. Below is a worked example, followed by a step-by-step guide to building one.
Sample — Progress Report No. 6, weighted progress
| Item | Description | ||||
|---|---|---|---|---|---|
| A — Substructure (weight 20%) | |||||
| A.1 | Excavation and foundations | ||||
| A.2 | Reinforced concrete footings | ||||
| Subtotal — Substructure | 19.0 | ||||
| B — Superstructure (weight 35%) | |||||
| B.1 | Blockwork walling | ||||
| B.2 | Reinforced concrete roof slab | ||||
| Subtotal — Superstructure | 17.5 | ||||
| C — Finishes (weight 25%) | |||||
| C.1 | Plastering and painting | ||||
| C.2 | Floor tiling | ||||
| Subtotal — Finishes | 0.8 | ||||
| D — MEP & external works (weight 20%) | |||||
| D.1 | Electrical and plumbing first fix | ||||
| D.2 | External works and landscaping | ||||
| Subtotal — MEP & external works | 0.6 | ||||
| Overall weighted progress (actual) | 37.9% | ||||
Progress summary — Report No. 6
Planned progress to date49.7%
Actual progress to date37.9%
Schedule variance-11.8%
Earned value (of USD 850,000 contract)USD 322,150.00
How to build a construction progress report
- 1List the work breakdown structure — sections and items — and assign each a weight (% of total contract value or effort), summing to 100%.
- 2Set the planned % complete for each item from the approved baseline programme/work plan for the reporting date.
- 3Record the actual % complete for each item, measured or assessed on site for the reporting date.
- 4Calculate earned % per item: weight × actual % complete.
- 5Sum earned % across all items for the overall actual progress to date, and do the same with planned % for the baseline.
- 6Compare actual vs planned to get the schedule variance, and flag the items furthest behind for corrective action.
- 7Convert earned % to earned value in money terms (weight × actual % × contract value) to report progress against the commercial baseline too.
- 8Issue the report on a consistent cycle — weekly or monthly — so the trend, not just a single snapshot, is visible over time.
Frequently asked questions
- What is a construction progress report?
- A periodic report — usually weekly or monthly — that states how much of the contracted work has been completed, broken down by section, and compares it against the planned schedule.
- What's the difference between planned % and actual % complete?
- Planned % is what the baseline programme says should be complete by the reporting date. Actual % is what has genuinely been measured or assessed as complete on site. The gap between them is the schedule variance.
- What is earned value in a progress report?
- Earned value converts physical progress into money: it's the weight (or BOQ value) of an item multiplied by its actual % complete, summed across the project. It lets you compare physical progress directly against amounts certified for payment.
- How often should progress reports be issued?
- Most contracts expect monthly reports alongside the payment certificate cycle; many project teams also track progress weekly internally to catch slippage earlier.
- Can progress reports be generated automatically from a BOQ or work plan?
- Yes — if items are already weighted (e.g. from a priced BOQ), the planned baseline can come from the work plan, and an engineer only needs to enter actual % or quantities each period rather than rebuilding the report from scratch.
Track progress without rebuilding the S-curve every period
Planovera ties your progress report straight to your BOQ or work plan — items are weighted automatically, you enter actual % or quantities, and the planned-vs-actual variance and earned value are calculated for you, period after period.
No credit card required
Related templates
Browse all templatesMore free templates for the same project
Bill of Quantities (BOQ)Free Bill of Quantities (BOQ) template and worked example for building and civil works — sections, items, units, quantities and rates, plus how to prepare one.View templateConstruction Work PlanFree construction work plan (programme) template — a worked activity schedule with durations and milestones, plus how to build one from a bill of quantities.View templateInterim Payment Certificate (IPC)Free interim payment certificate (IPC) template and sample for FIDIC-style construction contracts — line items, retention, advance recovery and net amount due, explained.View templatePractical Completion CertificateFree practical completion certificate template and worked example — what it certifies, what starts the defects liability period, and how retention is released.View template